Question: QUESTION 4 ( 2 0 Marks ) The table below gives the duration estimates in days for a construction projection. table [ [ Activity
QUESTION
Marks
The table below gives the duration estimates in days for a construction projection.
tableActivityPredecessor,Optimistic,Most Likely,PessimisticABCDAEAFBGCHEFIDJGKHJLI,K
Determine the expected completion time for each activity. Round off answers to the nearest whole
marks
number.
Construct an Activityonnode AON network for the activities of this contract.
marks
Determine the critical path for the project by calculating the slack for each activity.
marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
