Question: QUESTION 4 ( 2 0 Marks ) The table below gives the duration estimates in days for a construction projection. Activity Predecessor Optimistic Most Likely

QUESTION 4(20 Marks)
The table below gives the duration estimates in days for a construction projection.
Activity Predecessor Optimistic Most Likely Pessimistic
A -247
B -136
C -358
D A 91120
E A 257
F B 6920
G C 51022
H E, F 3512
I D 479
J G 6913
K H,J 346
L I,K 71023
4.1 Determine the expected completion time for each activity. Round off answers to the nearest whole
number.
(5 marks)
4.2 Construct an Activity-on-node (AON) network for the activities of this contract. (5 marks)
4.3 Determine the critical path for the project by calculating the slack for each activity. (10 marks)
 QUESTION 4(20 Marks) The table below gives the duration estimates in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!