Question: Question 5 Table 2 shows the activities, predecessors and time estimates (in months) of a work package of the construction project. Required: 1. Draw a

Question 5

Table 2 shows the activities, predecessors and time estimates (in months) of a work package of the construction project.

Required:

1. Draw a network diagram (using the activity-on-node method) for the project.

2. Identify the critical path and calculate the expected duration to complete the project.

3. Calculate the probability of completing the project in 17 months

4. Calculate the probability of completing the project in 14 months.Question 5 Table 2 shows the activities,

Table 2: Activities, predecessors and time estimates of a work package Activity Predecessor Optimistic Likely Pessimistic A 2 3 4 B A 3 4 5 A 1 2 3 D B 3 5 7 E 3 4 5 F D, E 2 3 4

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!