Question: Question 4 2 0 Points Develop MRP records for all items needed for item F in the following product structure for product H , using

Question 4
20 Points
Develop MRP records for all items needed for item F in the following product structure for product H, using the information provided in the following tables. The lead time to complete product H is one week. Master production schedule (MPS) calls for 170,130, and 60 units of demand for period 4,5, and 6.
Planning Data
Data Category
D
E
F
G
I
Lot size rule
Q=15*
L4L
L4L
Q=300*
L4L
Lead time
2 weeks
1 week
1 week
2 weeks
2 weeks
Safety stock
15**
25
20
35
0
Scheduled receipts
None
none
1,300(wk 1)
700(wk 1)
900(wk 1)
Beginning inventory
30
40
20
50
0
*Planned order schedules must be the same or multiples of Q amount
**minimum on hand (ending inventory) quantity to be observed
FORMAT FOR ENTRIES: All quantities are INTEGER (120, for example). Enter 0 if you do not have quantity for any period.
PROVIDE THE FOLLOWING SELECTED VALUES:
Planned Order Release Quantities for Product H
Period 1
Period 2
Period 3
Period 4
Period 5
0
0
170
130
60
Gross Requirements Quantities for Item F
Period 1
Period 2
Period 3
Period 4
Period 5
Blank 6
Blank 7
Blank 8
Blank 9
Blank 10
Blank 1Blank 2Blank 3Blank 4Blank 5Blank 6Blank 7Blank 8Blank 9Blank 10
Question

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!