Question: Question: 4 . 2 The following Table contains activities that must be completed to finish a project. Associated with the activities are activity times, variances

Question:
4.2
The following Table contains activities that must be completed to finish a project. Associated with the activities are activity times, variances and immediate predecessors.
\table[[Activity,\table[[Activity],[Time]],\table[[Activity],[Variance]],\table[[Immediate],[Predecesso]]],[A,8,2,--],[B,7,1,-],[C,13,3,A],[D,10,2,B],[E,11,2,C],[F,14,4,D],[G,13,1,E],[H,11,2,F]]
Using the table above draw the network diagram. From the diagram drawn - determine:
A) The number of paths.
B) The critical path.
C) The length of the critical path.
D) Determine if shortening activity
E by
2 decreases the project time.
 Question: 4.2 The following Table contains activities that must be completed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!