Question: Question: 4 . 3 The following Table contains activities that must be completed to finish a project. Associated with the activities are activity times, variances
Question:
The following Table contains activities that must be completed to finish a project. Associated with the activities are activity times, variances and immediate predecessors.
tableActivitytableActivityTimetableActivityVariancetableImmediatePredecessoABCADBECFDGEHF
Using the table above draw the network diagram. From the diagram drawn determine:
A The number of paths.
B The critical path.
C The length of the critical path.
D Determine if shortening activity
B by
decreases the project time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
