Question: Question 4 ( 20 points). A. According to the figure below, which activities belong to the critical path? List the name of activities. For example:

Question 4 ( 20 points). A. According to the figure below, which activities belong to the critical path? List the name of activities. For example: Evaluate Freezers; Chart Temperatures, Review Service Record, etc. B. In general, should activities on the critical path be outsourced? Why or why not? Evaluate freezers Chart temperatures Review service record Consult with HVAC engineer Develop construction plan Complete IC assignment Complete ROI analysis Conduct regulatory review Obtain construction approva