Question: Question 4 (25 Marks) Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time.

Question 4 (25 Marks) Draw the network corresponding to the following information. Also, complete the table, identify the critical path, and specify project completion time. Activity Immediate Predecessor(s) Time (Weeks) A B 14 D B JE B LO IF C D 16 G P, E 18 H GF Activity Earliest Start Earliest Finish Latest Start Latest Finish Slack B D JE IF G H
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock