Question: Question 4 3 2 pts Projects often include indirect costs that are necessary to keep the organization running, but are not associated with one specific
Question
pts
Projects often include indirect costs that are necessary to keep the organization running, but are not associated with one specific project. Which of the following items are most typically considered to be indirect costs?
Travel cost for the project team
Costs associated with material and purchased parts
The cost of labor provided by project team members, consultants, and subcontractors
Executive salaries, utilities, insurance and clerical assistance