Question: When you have more than one agile team working on a single product, which one of the following should be considered? Select only one
When you have more than one agile team working on a single product, which one of the following should be considered? Select only one answer. All learns need to have similar agile maturity. Teams must participate together in all the agile events. Teams to have regular sync-up meels to manage and reduce the dependencies.