Question: Question 4 4 . 1 Calculate the total E 8 0 s of the below truck. Assume a damage factor of 4 . 0 4

Question 4
4.1 Calculate the total E80s of the below truck. Assume a damage factor of 4.0
4.2 The sketch below shows the timing, initial traffic loading and traffic growth factors of a road project in the Southern African region.
4.2.2 Conduct sensitivity analysis by considering annual traffic growth rates of 6% and 8% during SDP. Also provide a comment on your result.
(8)
4.2.3 What type of maintenance will be needed by the end of the year 2041?
4.3 Soil samples were obtained at 100 m intervals for a newly planned category (B) road in a wet region. The measured CBR values are 10,12,11,11,9,11,13. Calculate the design CBR and provide a neat, labelled freehand sketch showing your subgrade design.
4.4 Use TRH4 method to provide all possible alternative pavement structures for a road category C planned in a wet region. The cumulative traffic over 15 years SDP =2.9 million E80s and subgrade design is SG3. Show your work on the design tables and catalogues. Also, draw neat free-hand sketches to present the alternative pavement structures including the subgrade layers. The sketch must indicate pavement layers' names, materials, and layer thicknesses.
(22)
Question 4 4 . 1 Calculate the total E 8 0 s of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!