Question: Question 4 A budget that is created by starting with the work breakdown structure, determining costs for each work package, and Not yet answered then

Question 4 A budget that is created by starting

Question 4 A budget that is created by starting with the work breakdown structure, determining costs for each work package, and Not yet answered then adding these costs together is: Marked out of 1.00 Select one: P Flag question a. Top-down budgeting. b. Zero-based budgeting. c. Activity-based budgeting. d. Bottom-up budgeting. Question 5 Not yet answered Marked out of 1.00 P Flag question a. Alpha b. Gaussian c. Normal d. Binomial e. Beta