Question: CASE STUDY [30 Marks] A computer network company installs network points. The project manager has been very concerned with the amount of time it took

CASE STUDY [30 Marks] A computer network company installs network points. The project manager has been very concerned with the amount of time it took to complete several recent jobs. The data obtained (all in days) for a new contract are listed in the following table: Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A --------- 4 6 8 B --------- 2 4 6 C --------- 1 2 3 D B 6 7 8 E A 2 4 6 F E 6 10 14 G D 1 3 5 H C,D 3 6 9 I F, G, H 5 11 17 Answer ALL the questions in this section. Question 1 (10 Marks) Calculate the expected time of activities for this project. Question 2 (10 Marks) Construct an AON network for the activities of this contract. Question 3 (10 Marks) Determine the critical path for the project using slack.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!