Question: Question 4 : A DC center uses a double order point system. Its replenishment orders come from the Central Supply. The weekly demand of the

Question 4: A DC center uses a double order point system. Its replenishment orders come from the Central Supply. The weekly demand of the DC is 150 units, the manufacturing lead time is 2 weeks, and the replenishment lead time is 1 week. If the safety stock is 30 units, determine: (2.5 marks)
1- The stock level at which the DC provides a warning to the Central Supply
2- The stock level at which the DC send the order to the Central Supply

Step by Step Solution