Question: Question - 4 Draw a CPM network diagram using the data in the table below. Use PDM format to show Activity ID , Description, Original
Question
Draw a CPM network diagram using the data in the table below. Use PDM format to show Activity ID Description, Original Duration OD Total Float TF Early Start ES and Early Finish EF
tableIDDescription,Duration,RelationshipNTP Notic to proceed,Milestone,No other activity can start until NTP issuedMobilize to site, WDSucceeds finish of activity Bid and select subcontractor, WDSucceeds finish of activity Deliver owner equipment, WDSucceed finish of activity by daysConstruct foundation, WDSucceeds finish of activity Install equipment,,Succeeds finish of activity Connect and install controls, WDSucceed start of activity by daysStart and test equipment, WDSucceed finish of activity and Mechanical completion,Milestone,Succeed finish of activity Commission equipment, WDSucceed finish of activity Final completion,Milestone,Succeed finish of activity
WD Workday Day Workweek, Friday the weekend
NTP Issued Tuesday, January
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
