Identify the ONE INCORRECT statement regarding Project Scope Management. Group of answer choices A. The importance of
Fantastic news! We've Found the answer you've been seeking!
Question:
Identify the ONE INCORRECT statement regarding Project Scope Management.
Group of answer choices
A. The importance of this phase of the project is to gather all of the requirements for the project.
B. The true measure of success for a PM is that once the requirements are agreed upon in Scope Management, the PM should not let them ever change throughout the rest of the project.
C. The major deliverable from this phase of the project is the Requirements Traceability Matrix.
D. Planning Scope Management is the most important part of the what the PM should do
during the Scope Management phase.
Related Book For
Project Management A Systems Approach to Planning Scheduling and Controlling
ISBN: 978-0470278703
10th Edition
Authors: Harold Kerzner
Posted Date: