Question: Question 4 In order for the project manager at Lebopo Pharmaceutical Co - operation ( LPC ) to complete the COVID - 1 9 clinical

Question 4
In order for the project manager at Lebopo Pharmaceutical Co-operation(LPC) to complete the COVID-19 clinical trials he has
to carry out the following activities indicated as A to G in the table below. The project leader has also compiled estimated
completion times (in weeks) as well as the immediate predecessors.
a) Construct the network AON diagram for LPC's COVID-19 trials project.(5 marks)
b) Calculate the earliest and latest start and finish times for all activities(8 marks)
c) Determine the critical path for the COVID-19 trials project.(2 marks)
d) Determine the expected project completion time.(2 marks)
e) Calculate the variance for each activity.(4 marks)
f) Find the probability of completing the COVID-19 clinical trials 3 weeks earlier than the determined expected time.(4
marks)
 Question 4 In order for the project manager at Lebopo Pharmaceutical

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!