Question: Question 4 In order for the project manager at Lebopo Pharmaceutical Co - operation ( LPC ) to complete the COVID - 1 9 clinical
Question
In order for the project manager at Lebopo Pharmaceutical CooperationLPC to complete the COVID clinical trials he has
to carry out the following activities indicated as to in the table below. The project leader has also compiled estimated
completion times in weeks as well as the immediate predecessors.
a Construct the network AON diagram for LPCs COVID trials project. marks
b Calculate the earliest and latest start and finish times for all activities marks
c Determine the critical path for the COVID trials project. marks
d Determine the expected project completion time. marks
e Calculate the variance for each activity. marks
f Find the probability of completing the COVID clinical trials weeks earlier than the determined expected time.
marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock