Question: Question 4 Table 4 shows the schedule for a project whose main resources are 3 engineers. Activities A and D require 1 engineer to complete

Question 4 Table 4 shows the schedule for a

Question 4 Table 4 shows the schedule for a project whose main resources are 3 engineers. Activities A and D require 1 engineer to complete while activities B, C, E and F require 2 engineers each. Splitting of activities is not possible. (a) Draw the project network and resource graph and determine the project duration if resources are unconstrained. (8 marks) (b) Draw the resource graph and determine the project duration under the given constraint. (5 marks) (C) To maximize the chances of project success, the project manager undertook the process of risk management. Discuss the steps involved and derive a simple Risk Log for this project. (12 marks) Table 4 Activity Code Dependent Upon Duration (Days) Resource Required A None 4 1E B None 5 2E A 4 2E D A, B 5 1E E B 3 2E F C,D,E 2 2E Question 4 Table 4 shows the schedule for a project whose main resources are 3 engineers. Activities A and D require 1 engineer to complete while activities B, C, E and F require 2 engineers each. Splitting of activities is not possible. (a) Draw the project network and resource graph and determine the project duration if resources are unconstrained. (8 marks) (b) Draw the resource graph and determine the project duration under the given constraint. (5 marks) (C) To maximize the chances of project success, the project manager undertook the process of risk management. Discuss the steps involved and derive a simple Risk Log for this project. (12 marks) Table 4 Activity Code Dependent Upon Duration (Days) Resource Required A None 4 1E B None 5 2E A 4 2E D A, B 5 1E E B 3 2E F C,D,E 2 2E

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!