Question: Question 4 Use the information in the table below and answer the questions that follow: Activity Predecessor Time A 10 B 23 C 16 D
| Question 4 | ||||||
| Use the information in the table below and answer the questions that follow: | ||||||
| Activity | Predecessor | Time | ||||
| A | 10 | |||||
| B | 23 | |||||
| C | 16 | |||||
| D | A | 14 | ||||
| E | B | 15 | ||||
| F | C,E | 13 | ||||
| G | D | 15 | ||||
| H | F | 9 | ||||
| I | G,H | 4 | ||||
| 4.1 Draw the Activity on Node diagram for the above information | ||||||
| 4.2 Calculate the duartion of all possible paths on the network diagram | ||||||
| 4.3 Identify the critical path and state its duration | ||||||