Question: QUESTION 4 When using Unified Scheduling Method to determine the cost buffer, one should sort the activities on the critical path in descending order of
QUESTION 4
-
When using Unified Scheduling Method to determine the cost buffer, one should sort the activities on the critical path in descending order of cost errors and take the sum of cost errors of "a" activities from the top ("a" is the estimated number of activities that will exceed their budgeted cost).
True
False