Question: Question 4 Your team is calculating triangular distributions. Which of the following processes are they engaged in ? Control Schedule Estimate Schedule Sequence Activities Estimate
Question
Your team is calculating triangular distributions. Which of the following processes are they engaged in
Control Schedule
Estimate Schedule
Sequence Activities
Estimate Activity Durations