Question: Question 47 (1 point) OP = DDLT + SS Demand is 300 units a week, lead time is 3 weeks, and safety stock is 200

Question 47 (1 point) OP = DDLT + SS Demand is
Question 47 (1 point) OP = DDLT + SS Demand is 300 units a week, lead time is 3 weeks, and safety stock is 200 units. Calculate the order point? O 900 1000 1100 1200