Question: Question 5 0 . 5 p t s A scheduling rule used for sequencing jobs through two work centers such that makespan is minimized is
Question
A scheduling rule used for sequencing jobs through two work centers such that makespan is minimized is
slack per operation rule.
shortest processing time rule.
Johnson's rule.
critical ratio rule.
Pareto rule.