Question 5 0.5 points The "fast tracking" method of schedule compression involves:

Question 5 0.5 points The "fast tracking" method of schedule compression involves: Assigning "dedicated teams" to critical path activities to achieve project schedule objectives. The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned. Going on a "mandatory overtime schedule" to complete the project on schedule or earlier if possible. Performing in parallel for at least a portion of their duration activities or phases that are normally done in sequence, which may result in rework and increased risk.

Step by Step Solution

3.41 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

D Performing in parallel for at least a portion of their duration activities or phas... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!