Question: The fast tracking method of schedule compression involves: A. The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally
The ”fast tracking” method of schedule compression involves:
A. The use of industrial engineering techniques to improve productivity, thereby finishing the project earlier than originally planned.
B. * Performing in parallel for at least a portion of their duration activities or phases that are normally done in sequence, which may result in rework and increased risk.
C. Going on a ”mandatory overtime schedule” to complete the project on schedule or earlier if possible.
D. Assigning ”dedicated teams” to critical path activities to achieve project schedule objectives.