Question: Question 5) 1. Parametric cost estimates utilize a bottom-up approach True False 2. Engineering cost estimates require detailed designs True False 3. Rough order of

Question 5)

1. Parametric cost estimates utilize a bottom-up approach

True False

2. Engineering cost estimates require detailed designs

True False

3. Rough order of magnitude estimates are most often associated with Parametric cost estimating

True False

4. Engineering cost estimates are quick and easy to develop

True False

5. Class 1 estimates are the initial/basic estimate, usually involving the largest range of error

True False

6. According to Standish, more than 50% of all IT projects experience cost overruns of 51% or more

True False

7. Tetlock believes Hedgehogs make better forecasters due to their cognitive style that is biased towards a single idea or approach.

True False

8. When developing a cost estimate, determining the estimates purpose is one of the most important steps

True False

9. Updating an estimate is recommended only when it is easily achieved

True False

10. Analogy estimates are based upon years of highly accurate data, therefore is the gold standard whenever possible

True False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!