Question: Question 5 (1 point) Saved Which two tasks are near critical path (i.e. shortest non-zero slack)? Define customer problems (4) and Mass storage requirements (6)

Question 5 (1 point) Saved Which two tasks are

Question 5 (1 point) Saved Which two tasks are near critical path (i.e. shortest non-zero slack)? Define customer problems (4) and Mass storage requirements (6) Define customer problems (4) and Compile vendor list (12) Mass storage requirements (6) and Compile vendor list (12) Define customer problems (4) and Compare system "philosophies