Question: Question 5 ( 1 point ) Which project management process groups must be included in every project? Initiating, planning, executing, and closing Initiating, costing, scheduling,
Question point
Which project management process groups must be included in every project?
Initiating, planning, executing, and closing
Initiating, costing, scheduling, phlanning, and executing
Initiating, planning, executing, monitoring and controlling, and closing
Feasibility, planning, executing, and monitoring and controlling