Question: QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you
![QUESTION 5 [10] For a particular work package, the budgeted cost](https://s3.amazonaws.com/si.experts.images/answers/2024/07/668b919f4311e_814668b919ed2747.jpg)
QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you as the project manager determines that only 85% of the scheduled work has been completed and the actual expense is R22 000 . 5.2.1. Determine the BCWP, BCWS, and ACWP. (3) 5.2.2. Calculate AV,SV,CV,SPI, and CPI for the work package. Explain the progress made. (7)