Question: QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you

 QUESTION 5 [10] For a particular work package, the budgeted cost

QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you as the project manager determines that only 85% of the scheduled work has been completed and the actual expense is R22 000 . 5.2.1. Determine the BCWP, BCWS, and ACWP. (3) 5.2.2. Calculate AV,SV,CV,SPI, and CPI for the work package. Explain the progress made. (7)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!