Question: QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you

 QUESTION 5 [10] For a particular work package, the budgeted cost

QUESTION 5 [10] For a particular work package, the budgeted cost as of 1 October is R20 000. Assume that as of 1 September, you as the project manager determines that only 85% of the scheduled work has been completed and the actual expense is R22 000. 5.2.1. Determine the BCWP, BCWS, and ACWP. (3) 5.2.2. Calculate AV, SV, CV, SPI, and CPI for the work package. Explain the progress made. (7)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!