Question: Question 5 (10 Marks): A software development company's project manager wants to calculate the project's expected cost. The historical data shows each team member can

Question 5 (10 Marks): A software development company's project manager wants to calculate the project's expected cost. The historical data shows each team member can handle eight function points each person-month and the cost of each team member is $5,000/month. Element Input Output Inquiries Files Interfaces Count 10 4 4 28 18 Complexity Low Low High Medium High Using the complexity weighting" scheme discussed in the class and information provided in the above table: a. Compute the total number of function points. b. Estimate the total cost and time of the project. Note: . Please DO NOT submit an Excel file as your answers. Email submission WILL NOT be accepted. Good Luck