Question: Question 5 [ 2 5 Points ] Consider the following project: begin { tabular } { | c | c | c | c
Question Points Consider the following project:
begintabularccccc
hline multirow Activity & multirow Depends on & multicolumnc Activity Duration days
cline & & Optimistic & Most Likely & Pessimistic
hline A & & & &
hline B & & & &
hline C & A & & &
hline D & B & & &
hline E & CD & & &
hline F & B & & &
hline
endtabular
a Determine expected duration mathrmtmathrme and sigmamathrmTe for each activity. points
b Determine Te and sigmaTe points
c What is the probability that: points
i The project will be completed in days.
ii The project will be completed in more than days.
iii. The project will take between and days.
d If the owner wishes to work on a probability of completion of what will be the earliest project time? points
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
