Question 5[25 Points] Consider the following project:
\begin{tabular}{|c|c|c|c|c|}
\hline \multirow{2}{*}{ Activity } & \multirow{2}{*}{ Depends on } & \multicolumn{3}{|c|}{ Activity Duration (days)}\\
\cline {3-5} & & Optimistic & Most Likely & Pessimistic \\
\hline A & - & 2 & 5 & 14\\
\hline B & - & 3 & 12 & 21\\
\hline C & A & 5 & 14 & 17\\
\hline D & B & 2 & 5 & 8\\
\hline E & C,D & 1 & 4 & 7\\
\hline F & B & 6 & 15 & 30\\
\hline
\end{tabular}
a) Determine expected duration \(\mathrm{t}_{\mathrm{e}}\) and \(\sigma_{\mathrm{Te}}\) for each activity. (5 points)
b) Determine \( T_{e}\) and \(\sigma_{T_{e}}\)(5 points)
c) What is the probability that: (15 points)
i. The project will be completed in 25 days.
ii. The project will be completed in more than 30 days.
iii. The project will take between 26 and 30 days.
d) If the owner wishes to work on a probability of completion of 0.8, what will be the earliest project time? (5 points)
 Question 5[25 Points] Consider the following project: \begin{tabular}{|c|c|c|c|c|} \hline \multirow{2}{*}{ Activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!