Question: QUESTION 5 ( 2 marks ) [ 1 0 MARKS ] Fundile is constructing a network for project Topnotch. As project manager she needs to
QUESTION
marks
MARKS
Fundile is constructing a network for project Topnotch. As project manager she needs to know all the tasks that must be completed to finalise the transport project. Once plotted, activity durations are calculated before she can determine early and late starting times, slack for each activity, project completion date and the critical path.
Propose the required formula used to calculate the expected time for an activity.
marks
Compile the key supporting the formula, indicating the meaning of each element of the formula provided in
marks
Calculate the expected time for activity considering the following information available on project Topnotch, where days; days; and days.
marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock