Question: Question 5 2 pts When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget
Question
pts
When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then go ahead with the work without customer approval.
True
False