Question: Activity: A, B, C, D, E, F, G, Finish Precedent: start, A and E, B, C, start, A and E, F and B, D and

Activity: A, B, C, D, E, F, G, Finish

Precedent: start, A and E, B, C, start, A and E, F and B, D and G

Duration: 6, 2, 2, 3, 1, 1, 7, 0

1a.) Using the above table draw the network diagram

1b.) Using the above table, identify the activities on the critical path in sequence

1c.) lf activity D takes twice as long describe the effect on the schedule

1d.) Calculate the earliest finish for Task B if its predecessor, Task A, finishes on day 3 and the duration of Task B is 2 days.

a. day 5 b. day 3

c. day 1

d. Cannot be calculated based upon information given.

1e.) When the customer requests a change, the contractor or project team should estimate the impact on the project schedule and budget and then go ahead with the work without customer approval.

True or False

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!