Question: Question 5 (20 points) Consider the following software development project with the following network. Activity Name B D E F Activity Duration (Months) 2. 3

Question 5 (20 points) Consider the following software development project with the following network. Activity Name B D E F Activity Duration (Months) 2. 3 3 4 2 1 Immediate Preceding Activity None None B. A C B D You are to do as follows: i. Draw the PERT/CPM diagram that fits the table of description above ii. Determine the critical path of this project. Give a reason for your selection. iii. Determine the Earliest and Latest Completion Times (ECT/LCT) for every node