Question: Question 5 [20] Refer to the project information given below and answer the questions that follow: Activity ID Predecessor Duration (in days) A 2 B
![Question 5 [20] Refer to the project information given below and](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/10/67022c1a29a78_60967022c19b82ff.jpg)
Question 5 [20] Refer to the project information given below and answer the questions that follow: Activity ID Predecessor Duration (in days) A 2 B 3 1 2 E B,C 2 G D, E 4 H F G 5 I H 1 D B B 4 : 4.1 Construct a network diagram using the Activity-on-the-node method. Indicate the ES, EF, LS and LF times for each activity on the network diagram. Also calculate the slack for each activity. (16) 4.2 Determine the critical path. (2) 4.3 If Activity E took an extra day to complete, what would the impact on your project duration be? Why? (2)