Question: Question 5 (25 points) Please calculate BCWP, BCWS, EAC, SV, and CV of the project with the following information Five-month project Current time: End

Question 5 (25 points) Please calculate BCWP, BCWS, EAC, SV, and CV

Question 5 (25 points) Please calculate BCWP, BCWS, EAC, SV, and CV of the project with the following information Five-month project Current time: End of third month Current cost: $102,000 Activity Status as of now (End of the third month) o Site work: 100% o Excavation 90% o Foundation 85% o Fencing 70% Paving 65% Framing 20% Drywall 10% Activity Budgeted Cost 2 4 5 Sitework $22,000 Excavation $10,000 Foundation $18,000 Fencing $30,000 Paving $50,000 Framing $40,000 Drywall $13,000