Question: please include work thankyou Please calculate BCWP, BCWS, EAC, SV, and CV of the project with the following information - Five-month project - Current time:

please include work thankyou
Please calculate BCWP, BCWS, EAC, SV, and CV of the project with the following information - Five-month project - Current time: End of third month - Current cost: $102,000 - Activity Status as of now (End of the third month) - Site work: 100% - Excavation 90% - Foundation 85% Fencing 70% Paving 65\% Framing 20\% Drywall 10%