Question: Question 5 4 1 Point l n the customer usually requires that, throughout the project, the contractor regularly compares actual expenditures with the proposed budget
Question
Point
the customer usually requires that, throughout the project, the contractor regularly compares actual expenditures with the proposed budget and reforecasts cost atcompletion, comparing it with the original proposed price.
cost reimbursement contracts
fixed agreements
fixed price contracts
work agreements