Question: Question 5 4 The earliest start time for an activity is equal to the: largest earliest finish time of all of its immediate predecessors largest
Question
The earliest start time for an activity is equal to the:
largest earliest finish time of all of its immediate predecessors
largest late finish time of all of its immediate predecessors
smallest late start time of any of its immediate predecessors
smallest earliest finish time of all of its immediate predecessors