Question: This assignment is worth 10 points. The table below details the steps required to build and begin services at a new hospital. Use the information
This assignment is worth 10 points. The table below details the steps required to build and begin services at a new hospital. Use the information in the table below to:
- Develop a process flow chart
- Use the critical path method to determine the process flow time
- Answer the questions
1. What is the earliest start time (EST) of Activity C?
2. What is the earliest finish time (EFT) of Activity G?
3. What is the latest finish time (LFT) of Activity D?
4. What is the slack for Activity F?
5. What is the flow time of the process?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
