Question: Question 5 A partial information about a project is shown below. Activity M; 50 days; IP = G, H Activity N; 23 days; IP =

Question 5 A partial information about a project
Question 5 A partial information about a project is shown below. Activity M; 50 days; IP = G, H Activity N; 23 days; IP = G, H Activity P; 35 days; IP = K Activity Q: 41 days; IP = M Activity R; 62 days; IP = N, P It has been calculated that LF(Q) = 190 and LF(R) = 206. Find the value of LF(G)