Question 5 Agatha is a principal project manager

Question 5 Agatha is a principal project manager managing a six-month project for his organization. This latest project pairs him with a project sponsor who is notorious for allowing scope creep to occur in her projects. For this reason, Nicolas is likely to place greater emphasis on what project management process? A. Plan Scope Management B. Validate Scope C. Control Scope D. Control Quality