Question: QUESTION 5 Calculate the earliest finish time for node 8 and explain and sign the related correct answers B E/5 4 3 D 1 WD

QUESTION 5 Calculate the earliest finish time for

QUESTION 5 Calculate the earliest finish time for node 8 and explain and sign the related correct answers B E/5 4 3 D 1 WD 2 3 13 G6 3 NI H J 5 6 7) 8 3 2 2 a. The earliest finish time for node 4 is 4 b. The earliest finish time is 20 c. Activity I can be late by 1 unit without delaying the project d. The earliest finish time is 13 e. The path to earliest finish time for node 8 is the "Critical Path