Question: Table 2 shows the activities, predecessors and time estimates (in months) of a work package of the construction project. Table 2: Activities, predecessors and time
Table 2 shows the activities, predecessors and time estimates (in months) of a work package of the construction project.

Table 2: Activities, predecessors and time estimates of a work package Activity Predecessor Optimistic Likely Pessimistic
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
