The five project management process groups as described in the PMBOK Guide and discussed in the preceding lesson are:
Status: object Object
point
Initiating, planning, executing, monitoring and controlling, closing
Kickoff, requirements, plan, schedule, control
Requirements, design, development, testing, implementation
Define, measure, analyze, improve, control