Question: Question 5 The table below lists three time estimates and the immediate predecessor ( s ) for each activity in a construction project that is

Question 5
The table below lists three time estimates and the immediate predecessor(s) for each activity in a construction project that is to be
scheduled using PERT. The three time estimates (in weeks) are in the order: optimistic time, most likely time, and pessimistic time.
The total variance of the critical path is equal to
2.36
4.39
1.54
3.82