Question: The table below lists three time estimates and the immediate predecessor ( s ) for each activity in a construction project that is to be

The table below lists three time estimates and the immediate predecessor(s) for each activity in a construction project that is to be scheduled using PERT. The three time estimates (in weeks) are in the order: optimistic time, most likely time, and pessimistic time.
Activity
1
2
3
4
5
6
7
8
Time estimates (weeks)
1,2,3
3,5,7
5,7,9
5,7,12
1,2,3
2,3,4
7,9,11
1,3,8
Immediate predecessor
-
1
1
2
3
4,5
3
6,7
What is the probability that the project will be completed within 20 weeks?
45%
86%
31%
16%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!