Question: Question 5 Three models A, B, and C are to be assembled on a mixed line with production rates of 15,20 , and 25 unit/hr
Question 5 Three models A, B, and C are to be assembled on a mixed line with production rates of 15,20 , and 25 unit/hr respectively. The work elements, elements times and precedence requirements for the models are given in table (4). (i) Construct the precedence diagram for each model and the combined diagram. (ii) Assume line efficiency =0.96, reposition time =0.09min, and manning level =1.0. Determine the number of workstations required and its balance. (iii) If each workstation requires (2.51.5m) space with at least (0.5m) clearance between each station. Find the total area required for the assembly line. Assume any missing data